Copper repipe cost

Repiping a house in copper costs $8,000 to $22,000, typically $13,000, against $4,500 to $12,000 in PEX. Soldering labor is most of the gap, and extra wall openings add to both.

New copper water supply pipes with soldered fittings running through wall framing

National average

$13,000

per project

National estimate as of October 2026, not a quote. Where these figures come from.

Base pricing reviewed October 2026 · Labor: BLS OEWS May 2025 · Materials: BLS PPI August 2026

Repiping a house in copper costs $8,000 to $22,000, typically around $13,000 for a two-bathroom house. The same house in PEX runs $4,500 to $12,000, so copper carries a clear premium, and nearly all of it is labor: every joint is cut, cleaned, fitted and soldered by hand.

The other thing that moves a copper quote is the walls. Rigid pipe needs straighter routes and more openings than flexible tubing, and every opening has to be closed and finished again before the job is really done.

What it costs

LineCost
Whole-house copper repipe, supply lines$8,000 to $22,000
Copper repipe, typical$13,000
Same house in PEX$4,500 to $12,000
PEX repipe, typical$7,500
Extra wall opening, repaired and ready for paint, each$300 to $1,500
Plumber, per hour, for added work$75 to $150

Both repipe figures cover the supply lines from the main shutoff to every fixture, with routine drywall openings and patching. They do not cover drains, the water main from the street, or openings in tile and plaster beyond the usual, which are where the extra-opening line comes in.

Why copper still gets chosen

PEX is the default for most repipes now, and the whole-house repipe guide explains why. Copper is still picked for reasons that are real, if narrower.

Exposed runs. Copper is unaffected by sunlight. Pipe that runs through a sunny utility room, along an unfinished basement ceiling near windows, or outside the building envelope suits copper better than plastic.

Buyer expectations. In some markets and some price brackets, copper is still read as the quality option, and a listing that says copper repipe lands differently.

Local rules. A few jurisdictions, condominium associations and older building standards still specify copper for some or all supply piping. Check before choosing.

Electrical bonding. In many older houses the metal water pipe is part of the electrical grounding path. Replacing it with plastic breaks that path, and an electrician has to provide a bonding jumper or another grounding electrode. A copper repipe keeps the path continuous. It is not a reason on its own, but it is a cost a PEX quote often leaves out.

Rodents and heat. Copper cannot be chewed, and it tolerates heat near water heaters and boilers without the clearances some plastic tubing requires.

When copper is the wrong choice

Aggressive water. Water with low pH or high chlorides corrodes copper from the inside, and pinhole leaks are the result. If the old copper failed that way, new copper will follow it unless the water is treated. Test the water before choosing the same pipe again.

Pipes in unheated spaces. Copper splits when it freezes solid. PEX tolerates a freeze far better, though neither should be left to freeze.

A tight budget. The premium over PEX is large, and on most houses the water does not know the difference. Copper is a choice, not an upgrade every house needs.

The plumbing lifespan guide puts copper at 50 to 70 years, the longest of the common supply materials, but that range assumes water that does not attack it.

A plumber heating a copper fitting with a propane flame to solder a joint
Every joint in a copper repipe is cut, cleaned, fitted and soldered or pressed, which is why labor is most of the price.

Type L or Type M

Copper pipe comes in three common wall thicknesses, marked by printed color along the pipe.

Type K, green markings. The thickest wall, used mainly underground and for water services. Rarely used inside the house.

Type L, blue markings. The middle weight and the usual choice for a quality interior repipe. Some jurisdictions require it.

Type M, red markings. The thinnest wall. Allowed for interior residential supply in many places, cheaper per foot, and more vulnerable to pinholes where the water is aggressive.

The material difference between L and M is a modest part of a repipe, because labor dominates. Ask which type the quote assumes. If it says only "copper", it is probably Type M.

Soldered or press-fit. Most copper repipes are soldered with lead-free solder, as potable water rules have required for decades. Some plumbers use press fittings, which crimp onto the pipe with a powered tool and need no flame. The fittings cost more, the labor is faster, and there is no fire risk inside finished walls. Either is sound when done well.

Wall openings and patching

A PEX run can snake through a wall cavity from one opening. Copper needs a straight shot or a fitting at every turn, so a copper repipe usually opens more walls, at more places, than the same job in PEX.

Routine drywall openings are normally in the repipe price. What is often not:

  • Openings behind tile, such as a shower valve wall, which may mean opening from the room on the other side
  • Plaster and lath, which is slower to open and harder to match
  • Texture and paint, which some plumbers leave to you
  • Ceilings below a second-story bathroom

Each of those runs at about $300 to $1,500 per opening once it is repaired and ready for paint. Ask for a written count of expected openings and who closes them.

Why a copper quote expires sooner

Copper is a traded commodity, and its price moves with world markets in a way PEX does not. Supply houses reprice copper pipe and fittings often, sometimes weekly, and a plumber who held a number for three months can lose money on the job.

That is why copper repipe quotes often carry a short validity window, or a clause that adjusts the material line if the supplier's price changes before the pipe is bought. Ask how long the price holds and whether material is bought at signing or at the start of work. On a large house the material share is big enough that the answer matters.

A worked example: copper or PEX in the same house

A two-story, 1,800 square foot house with two bathrooms has galvanized supply pipe. The plumber expects two openings behind tile or plaster beyond the routine ones, possibly three. The owner asks for the job priced both ways.

In copper:

  • Copper repipe: $8,000 to $22,000
  • Extra openings: 2 to 3 openings × $300 to $1,500 each = $600 to $4,500
  • Total: $8,600 to $26,500

In PEX:

  • PEX repipe: $4,500 to $12,000
  • Extra openings: 2 to 3 openings × $300 to $1,500 each = $600 to $4,500
  • Total: $5,100 to $16,500

The opening lines are written the same for both, though in practice the copper job may need more. The gap between the totals is mostly soldering labor. On this house, copper is the right call only if one of the reasons above applies. Otherwise the difference buys nothing the water will notice.

Questions to ask on a copper repipe quote

  • Type L or Type M, and soldered or press-fit?
  • How many wall openings, where, and is patching, texture and paint included?
  • Is the electrical bond checked or restored?
  • Does the price include new shutoff valves at every fixture?
  • Who pulls the permit and arranges the inspection?

Frequently asked questions

How much does it cost to repipe a house with copper?

$8,000 to $22,000, typically about $13,000 for a two-bathroom house. Fixture count, the number of stories and plaster or tile walls push it toward the top. Extra openings beyond the routine ones are usually priced separately.

Is Type L or Type M copper better for a house?

Type L has a thicker wall and is the better choice for longevity, especially where water chemistry is a concern. Type M is permitted for interior supply in many jurisdictions and costs less per foot. Since labor dominates a repipe, the upgrade to L adds relatively little.

Is a copper repipe worth it over PEX?

For most houses, no: PEX does the same job for much less. Copper is worth it for exposed runs, local rules that require it, buyer expectations in certain markets, or where the grounding path through the pipe matters.

Why does copper repiping cost so much more than PEX?

Every joint in copper is cut, cleaned, fitted and soldered or pressed, while PEX runs in long continuous lengths with few joints. The material also costs more. Labor is the larger share of the difference.

What this costs in your state

Priced from the mean hourly wage for plumbers, pipefitters and steamfitters in each state against the national mean, BLS OEWS May 2025. Only the labor part of the figure moves: about 50% of this job is labor, so a state paying 20% above the national mean lands about 10% above the national price rather than 20%. Materials cost much the same everywhere.

Typical per project cost by state, most expensive first
StateTypicalRangeWage index
Oregon$15,366$9,456 to $26,0041.36×
Illinois$14,913$9,177 to $25,2371.29×
New Jersey$14,838$9,131 to $25,1101.28×
District of Columbia$14,714$9,055 to $24,9011.26×
Alaska$14,647$9,013 to $24,7861.25×
Show the other 41 states
StateTypicalRangeWage index
Massachusetts$14,641$9,010 to $24,7771.25×
Washington$14,497$8,921 to $24,5331.23×
Minnesota$14,307$8,805 to $24,2131.20×
Wisconsin$14,130$8,695 to $23,9121.17×
New York$14,047$8,644 to $23,7721.16×
Hawaii$13,957$8,589 to $23,6201.15×
California$13,914$8,563 to $23,5471.14×
Rhode Island$13,849$8,522 to $23,4361.13×
Montana$13,541$8,333 to $22,9161.08×
Michigan$13,457$8,281 to $22,7731.07×
Pennsylvania$13,440$8,271 to $22,7451.07×
Indiana$13,313$8,193 to $22,5291.05×
Connecticut$13,290$8,179 to $22,4911.04×
Missouri$13,255$8,157 to $22,4311.04×
Maryland$13,120$8,074 to $22,2031.02×
Nevada$12,940$7,963 to $21,8990.99×
Kansas$12,931$7,957 to $21,8830.99×
Iowa$12,807$7,881 to $21,6730.97×
Ohio$12,777$7,863 to $21,6230.97×
Colorado$12,723$7,829 to $21,5310.96×
Vermont$12,712$7,822 to $21,5120.96×
Kentucky$12,702$7,817 to $21,4960.95×
Delaware$12,635$7,775 to $21,3820.94×
Arizona$12,618$7,765 to $21,3530.94×
Maine$12,494$7,689 to $21,1440.92×
New Hampshire$12,464$7,670 to $21,0930.92×
North Dakota$12,459$7,667 to $21,0840.92×
Nebraska$12,417$7,642 to $21,0140.91×
Utah$12,283$7,559 to $20,7860.89×
Louisiana$12,140$7,471 to $20,5450.87×
Wyoming$12,075$7,431 to $20,4340.86×
New Mexico$12,065$7,425 to $20,4180.86×
Texas$11,973$7,368 to $20,2630.84×
Virginia$11,962$7,361 to $20,2440.84×
Tennessee$11,949$7,353 to $20,2220.84×
Oklahoma$11,811$7,268 to $19,9870.82×
West Virginia$11,794$7,258 to $19,9590.81×
Idaho$11,764$7,239 to $19,9080.81×
Georgia$11,743$7,227 to $19,8730.81×
Alabama$11,702$7,201 to $19,8030.80×
North Carolina$11,608$7,144 to $19,6450.79×

Least expensive

StateTypicalRangeWage index
Mississippi$11,604$7,141 to $19,6380.79×
Florida$11,546$7,105 to $19,5400.78×
South Carolina$11,533$7,097 to $19,5180.77×
South Dakota$11,501$7,078 to $19,4640.77×
Arkansas$11,061$6,807 to $18,7190.70×

All 50 states and the District of Columbia. BLS suppresses an estimate where the sample is too small to publish, and those are left out rather than filled in with the national figure.

Producer price index for copper and brass mill shapes

This is a materials cost trend, not a project price. It is what producers charge for the material, indexed to a base year — useful for seeing which way the material behind this job has moved, and not a figure to multiply anything by.

263419574202120222023202420252026
WPU1024 is 36.6% higher than twelve months ago, which moves the materials part of this job and not the labor. Source: BLS series WPU1024.

Sources and methodology

Labor
Plumbers, pipefitters and steamfitters (SOC 47-2152) — BLS OEWS, May 2025
Materials
Copper and brass mill shapes (BLS PPI WPU1024, August 2026)
Split
About 50% of this figure is labor and 50% materials, which is what decides whether it moves with wages or with the commodity index. How we calculate costs.